Please note, dates are subject to change depending on weather and contractor availability.

 
  • Design and permitting

    June 2021-November 2021
  • Utility relocations

    October 2021-March 2022
  • Construction bid period

    November 2021-December 2021
  • Construction start

    February 2022
  • Construction end

    October 2022